Polypropylene Plant Extrusion and Pneumatic Handling System Relocation Project

Approximate Total Installed Cost: 40,000,000

Year: 2007

Plant Location: Netherlands/Texas

ECI Scope: Engineering/Design (Conceptual through Detail), Procurement, Construction Management, Startup Support

Project Scope Highlights:

  • Relocated entire extrusion and pneumatic transfer/material handling system from Europe to Texas
  • Designed new E&I, Additional Piping, new building/structure/foundations, and railway spur
  • Modified entire extrusion facility to current US codes.
  • Enabled 6 month earlier plant startup